Vigan Rewire - ADM

Vigan Rewire - ADM

On-going - To wire machine whilst still in use, The aim is to release and tepoparliy tie all existing cables off existing containment to allow us to pull all new cables to existing and new junction boxes, gland, prepare and connect where possible, all cables to be tested once glanded, a 3 week shut down for change over, working 24hrs a day 7 days a week to disconnect and remove existing panel, soft start panel, 2 blowers, 250kw motor, then install new panel, 2 VSD panels, 2 250kw motors, new CCTV system and fully commission with manufacturer VIGAN

Oil Seperation project - ADM

Oil Seperation project - ADM

Completed - Installation of new Auto valves, new flow meters, new instrumentation conduits, commissioning of existing instrumentations and new instrumentation, installation of 3 new motor supplies

Solvent Extraction plant - ADM - Explosion fire damage

Solvent Extraction plant - ADM - Explosion fire damage

24hr/7day a week for 5 months to fully decommission and re-install new containment across the plant, installation of new lighting design, installation of safety switches, installation of instrumentation, approx. 80km of cabling installed, Atex certified

Salmonella prevention silo aspiration - ADM

Salmonella prevention silo aspiration - ADM

Budget - 70k - Completed - Requirements - Installation of various size containment, Installation of zone 22 products, Installation of Control panel, Installation of cabling, Installation of transit frame, Installation of trace heating, Inspection and testing, Commissioning of aspiration fans and trace heating, Sign off from Z tech for Atex installation.

Lighting upgrade Pallet Warehouse and offices - Unilever

Lighting upgrade Pallet Warehouse and offices - Unilever

Budget - £70k - Completed - Requirements - Use of MEWP's whilst in live forklift area, Removal of existing 8ft fluorescent, installation of new lighting trunking and wiring, installation of Dextra Vertico lighting, installation of office lighting, commissioning of Vertico lighting sensors - 1 and half year return on investment

CHP (Combined heat and power) plant - ADM

CHP (Combined heat and power) plant - ADM

Budget - £750k - Completed - Requirements - Installation of MCC, Installation of VFD's, Installation of small power, Installation of instrumentation and PLC wiring, Connections to Saake Boilers, Installation of Hi bay/ general/ emergency lighting, Installation of UPS, Installation of temporary site power and lighting during early construction

Soap Splitting - ADM

Soap Splitting - ADM

Budget - £200k - Completed - Requirements - Installation of bespoke stainless steel containment, installation of MCC wiring and connections, installation of instrumentation and PLC wiring, installation of LED sensor lighting across 3 floors, Testing and inspection

Trace heat loading arms - IFC Inflow LTD

Trace heat loading arms - IFC Inflow LTD

Installation of trace heating to swing loading arms, Installation of Atex items, inspection of Atex installation, pre and post commissioning of insulation

Thermon

Thermon

Installation of trace heating to various clients around the UK, installation of Atex items, atex inspections, Pre and post insulation testing